Your organization is working with an international partner on a new and innovative product. All communication regarding this must be encrypted using a public domain symmetric algorithm. Which algorithm should you use?



Previous question and answer:

Taken from Cert-PMP4ED
Related Exam: PMI Cert-PMP4ED PMCert: Project Management Professional Fourth Edition
Item Number: Cert-PMP4ED.1.2.6


You are performing stakeholder analysis during the Identify Stakeholders process. You have decided to classify the stakeholders and group them based on their level of authority and level of concern. Which classification model are you using?


You are using the power/interest grid. This classification model classifies stakeholders based on their level of authority (power) and the level of concern (interest) regarding the project goals.

You are not using the Salience model. This model describes stakeholder classes based on their power, urgency, and legitimacy.

You are not using the influence/impact grid. This model classifies stakeholders based on their active involvement (influence) in the project and their ability to cause change to the project's execution (impact).

You are not using the power/influence grid. This model classifies stakeholders based on their authority (power) and the active involvement (influence) in the project.

References:

A Guide to the Project Management Body of Knowledge - PMBOK Guide 4th Edition - Project Communications Management - 10.1.2 Identify Stakeholders: Tools and Techniques



Previous Questions
05/24/2013
05/23/2013
05/22/2013
05/21/2013
05/20/2013
05/17/2013
05/16/2013
05/15/2013
05/14/2013
05/13/2013
05/10/2013
05/09/2013
05/08/2013
05/07/2013
05/06/2013
05/03/2013
05/02/2013
05/01/2013
04/30/2013
04/29/2013
04/26/2013